CorrectDeck® Composite Decking & Railing Systems

 

Return Home

Sitemap

Company Store

Distributor Login

Worldwide · FAQs

Products Installation Care & Upkeep Photos & Ideas Professionals Company Info Contact Us
Search CorrectDeck.com
Request a Sample

Installation

· Decking Installation

· Railing Installation

· Spacing Calculator

· Sizes & Specifications

· Installation FAQs


Quick Quote Form
Name:
Phone:
Email:
Company:
Inquiry Information:

Home > Products > RapidRail > Installing CorrectDeck RapidRail™

Installing CorrectDeck RapidRail™

 

These instructions are intended to guide you through the process of assembling your new CorrectDeck RapidRail system. While there are several ways of approaching this project, we have found this approach to be the simplest while insuring the final results will meet your expectations of a CorrectDeck product.

Gather 4x4 posts, top and bottom rails, hardware post caps and skirts, and carriage bolts appropriate for your framing from your RapidRail or RapidRail CX kit. The railings are pre-routed to accept the balusters, and are attached to the posts with angle brackets.

The guardrails come from the factory at 931/2"+ 1/2-0" long. The routed hole locations are calculated from the center of the rail out to each end, so you can use the guardrails for any span less than 8' by cutting an equal amount from both ends. Standard balusters come from the factory at 361/4" (371/2" for CX balusters) resulting in a 42" railing. For a 36" high railing, trim the standard balusters down to 301/4" (311/4" for CX balusters).

One squash block is required for all spans. Maximum post-to-post center distance is 8' (96"). This span uses a 921/2" guardrail; the guardrails come from the factory with some trim stock on each end, as do the posts which are 55"+1/2-0.

RapidRail™ Installation Video

Quicktime 7 is required to play video.
If you do not have Quicktime, click here to download the free player.

Additional Information:

RapidRail™ Installation Video

Installing 4x4 Post - Traditional Mount

Installing 4X4 Post - Optional Surface Base Mount Plate (After Decking Installation)

Complete Installation Instructions

Stair Rail Installation

Stair Rail CX Installation Video

RapidRail 45° Installation

Installation of Fascia/Skirting

 

1. Measure inside dimension from post to post and mark the centerline on deck. Match center of top and bottom rails to centerline between posts, by simply laying rails on deck and transferring the mark, or use a tape measure if you prefer.

2. Attach a 33/4" long support baluster (squash block) under the center of the bottom rail by drilling a 21/2" trim head screw down through the mortised hole in center of bottom rail. Note: when installing CX railing (above), the squash block is installed with a ball connector instead of the 21/2” trim head screw.

   

3. Mark holes, pre-drill and screw L-brackets to the underside of the bottom rail flush with the outside edges. The long side of L-bracket is installed to the rail. Pre-drill and screw bottom rail to posts.

Insert two balusters into routed holes at each end of the bottom rail section. and temporarily install top rail.

   

Mark locations for L-bracket holes on posts.

Remove top rail and pre-drill and screw brackets to posts.

   

Install remaining balusters into routed holes of the bottom rail.

Place top rail onto the L-brackets and insert balusters into the top rail.

   

Pre-drill and screw top rail to L-brackets at both post locations.

Install post caps & gently tap into place.

   

Tip For Hiding the Rail Brackets:

Some installers prefer to “hang” the rail system from brackets first installed on the posts. A benefit of this is that less of the upper bracket shows.

In order to get a tight fit between rail and post, it’s necessary to remove material from the end of the rail to accommodate the bracket. This can be done with a spade bit or a router.

Check to see that the L-bracket fits flush to the end of the rail. Install brackets to bottom rails in conventional manner.

 
 

 

Correct Building Products • 8 Morin Street • Biddeford, ME 04005
Toll Free: 1-877-332-5877 | Local: 207-284-5600 | Fax: 207-284-1001

 

©2006 Correct Building Products · About Us · Privacy · Search CorrectDeck.com

This site is optimized to work with Microsoft Internet Explorer 5.0, Netscape 6.0 and Mozilla Firefox 1.0. Website Plugins